HS2 Confirms Three M42 Weekend Closures from July 2026
HS2 confirmed three M42 weekend closures from 24–27 July 2026 to install 44 roof beams and move two 1,000-tonne viaduct spans into place near Solihull, England.

London, UK – HS2 engineers will close the M42 northbound between J6 and J9 and part of the M6toll from 24–27 July 2026 to install 44 pre-cast roof beams and move two 1,000-tonne viaduct spans into place near Solihull. The works form the first of three coordinated weekend closures in July, August and September, following a June closure that installed 50 of 175 beams. National Highways advises motorists to follow approved diversion routes and avoid sat nav directions.
What Is the Full Scope of This Project?
The full scope covers three structures over the M42: the twin box roof deck, Water Orton 1 viaduct extension, and Water Orton 2 viaduct extension, all being built on the 140-mile HS2 route between London and the West Midlands. The twin box structure will eventually carry trains over a 300-metre section of carriageway, with 175 pre-cast roof beams installed in phases; 50 were installed in June, and 44 more are targeted for the July closure. For the Water Orton viaducts, 108 segments are being assembled into six 45-metre-long spans, each weighing approximately 1,000 tonnes, and one span will be moved into place on each viaduct during the first closure using self-propelled modular transporters.
Key Project Data
| Parameter | Value |
|---|---|
| Project / Contract Name | HS2 M42 motorway crossing works – Water Orton viaducts and twin box structure |
| Total Value | Not disclosed |
| Parties Involved | HS2 Ltd; Balfour Beatty VINCI (BBV); Expanded; National Highways |
| Timeline / Completion | Three weekend closures: 24–27 July 2026; further August and September 2026 dates to be confirmed; subject to consent and change |
| Country / Corridor | United Kingdom; M42 between Solihull and Water Orton; HS2 Phase One London–West Midlands |
How Does This Compare to Similar Projects?
The M42 crossing package sits within HS2’s renegotiated civil engineering contract framework, which HS2 Ltd says was restructured to incentivise efficient delivery and cost control (Source: HS2 Ltd, 2025). In North America, the high-speed rail market is projected to reach USD 8.90 billion in 2026, driven by rail modernisation and infrastructure investment (Source: Mordor Intelligence, 2025). Canada’s Alto high-speed rail project advanced from concept to active development, with the Ottawa–Montreal corridor confirmed as the first section, showing that other high-speed rail programmes are moving from planning to site execution in the same period (Source: Railway Association of Canada, 2025). Amtrak’s NextGen Acela programme is a USD 2.45 billion rolling stock investment for 28 high-speed electric trains, but it does not provide a direct civil-structure cost benchmark for the M42 crossings (Source: Amtrak, 2024). Exact August and September closure dates for the M42 works were not disclosed.
Editor’s Analysis
Coordinating three structures under three weekend possessions signals that HS2 and National Highways are prioritising a compressed disruption window over repeated closures during a longer build period. The use of 1,000-tonne spans assembled off-line and moved by self-propelled modular transporters shows the growing shift toward modular construction on UK high-speed rail. This approach aligns with wider high-speed rail investment momentum in North America and Europe, where projects are now moving from planning approvals into physical works (Source: Railway Association of Canada, 2025).
FAQ
Q: Which M42 closures affect drivers on 24–27 July 2026?
A: The M42 will close northbound between J6 and J9 and southbound between J7a and J6, including the M6 J4a southbound link to the M42. The M6toll southbound at T2 will close from 10pm Friday until midday Saturday, and the M6toll northbound connecting road from M6 J3a to T1 will close all weekend.
Q: How many beams have been installed so far?
A: 50 of the 175 pre-cast roof beams were installed during the June 2026 closure. HS2 and Balfour Beatty VINCI targeted 44 additional beams for the 24–27 July 2026 northbound closure.
Q: What is the total cost of these M42 works?
A: HS2 Ltd and Balfour Beatty VINCI have not officially disclosed a total cost for this package. The works sit within HS2’s renegotiated civil engineering contract framework, which was restructured to control costs (Source: HS2 Ltd, 2025).