HS2 Completes 50% of 4.5-Mile London Euston Tunnels

HS2 Ltd confirmed 50 percent excavation progress on the 4.5-mile twin running tunnels linking Old Oak Common and London Euston ahead of completion in 2027.

HS2 Completes 50% of 4.5-Mile London Euston Tunnels
November 24, 2026 3:15 pm | Last Update: November 24, 2026 3:16 pm
A+
A-
⚡ In Brief: HS2 contractor Skanska Costain STRABAG JV reached the 50 percent completion milestone on the 4.5-mile London twin-bore running tunnels connecting Old Oak Common to Euston using two 1,624-tonne tunnel boring machines.

LONDON, UNITED KINGDOM – HS2 Ltd confirmed on 17 November that its twin tunnel boring machines, Karen and Madeleine, reached the halfway mark between West Hampstead and Kilburn High Road stations. The two 1,624-tonne machines are driving 4.5 miles of sub-surface running tunnels from Old Oak Common to Euston at an average advance rate of 16 metres per day. The drives form the final running tunnel section into central London, with underground arrival scheduled for 2027.

What Is the Full Scope of This Project?

The Euston tunnel drive requires twin-bore excavation generating 1.5 million tonnes of spoil and the installation of 48,294 precast concrete segment rings manufactured in Hartlepool. Skanska Costain STRABAG joint venture (SCS JV) operates both machines around the clock at depths reaching 50 metres beneath urban London. Upon completion in 2027, the 8.53-metre-diameter cutterheads will be dismantled and extracted via the Euston Cavern, while the external shields will remain permanently entombed behind the concrete tunnel lining. Redevelopment of the terminal precinct will transfer to the newly formed Euston Delivery Company, which oversees station integration across high-speed rail, London Underground links, and surrounding commercial real estate.

Key Project Data

ParameterValue
Project / Contract NameHS2 London Tunnels (Old Oak Common to Euston)
Total ValueNot disclosed
Parties InvolvedHS2 Ltd, Skanska Costain STRABAG JV (SCS JV), Euston Delivery Company
Timeline / CompletionTBM launch January–March 2026; tunnel drive completion scheduled for 2027
Country / CorridorUnited Kingdom / West Coast Main Line corridor relief (London Euston – West Midlands)

How Does This Compare to Similar Projects?

Tunnel advance rates on the Euston segment match standard dense-urban high-speed rail drives but face tighter fiscal limits seen across the global passenger rail sector. While SCS JV maintains 16 metres per day across London clay, the broader transit sector is contracting capital expenditure; the global metro subway market reached USD 18.5 billion in 2025, yet public authorities are curtailing runaway expansions due to operating deficits (Source: Industry Research Report, 2025). Major systems like the Shanghai Metro registered municipal operating subsidies of 17.583 billion yuan with revenue-expenditure gaps exceeding 40 percent (Source: 36Kr, 2025). Note: Independent verification of baseline civil contract figures for the January and March launch packages was not available at time of publication.

Editor’s Analysis

HS2 Ltd Chief Executive Mark Wild’s programme reset reflects an international shift toward capping fixed capital exposure on megaprojects before sub-surface risk triggers further budget escalations. Delegating the Euston terminal campus to a designated delivery vehicle isolates tunneling operations from station-box commercial liabilities while maintaining civil momentum toward central London. This approach aligns with global infrastructure patterns where state-backed sponsors partition core tunneling from commercial precinct development to attract private capital.

FAQ

Q: Where are the HS2 London tunnel boring machines currently located?
A: Both machines are advancing through the sub-surface zone between West Hampstead and Kilburn High Road stations in north-west London. They have completed 50 percent of their 4.5-mile drive from Old Oak Common toward Euston.

Q: When will the tunnel boring machines reach Euston station?
A: Excavation is scheduled to finish underground in 2027 on the approach to Euston Cavern. At that point, the cutterheads will be retrieved and the outer shields grouted into place.

Q: What happens to the soil excavated during the tunnel construction?
A: The machines will extract approximately 1.5 million tonnes of excavated material across the entire 4.5-mile alignment. The route will be lined using 48,294 precast concrete ring segments transported from a manufacturing facility in Hartlepool.

Railway infrastructure, rolling stock and transport technologies specialist focused on global rail industry developments, high-speed rail systems, signaling technologies and freight transportation. Covering railway investments, public transport modernization, rail operations and international mobility projects across Europe, Asia and North America.