Metrolinx completed a new Bloor GO tunnel and 2.5 km of track in Toronto, enabling four-track Kitchener Line service between Dupont Street and Lansdowne Avenue.

TORONTO, Canada – Metrolinx announced on July 31, 2026, that major upgrades at Bloor GO/UP Station are complete, including a new covered pedestrian pavilion and tunnel connecting the station to Randolph Avenue. The project delivered approximately 2.5 km (1.6 miles) of new GO Transit Kitchener Line track between Lansdowne Avenue and Dupont Street and realigned the West Toronto Railpath to create a new community park at Ernest Avenue. Additional works included a noise barrier, retaining wall, and taller fence along the west side of the Bloor Street West pedestrian bridge.
What Is the Full Scope of This Project?
The Bloor package bundles station-access infrastructure, community amenity space, and rail-corridor capacity improvements into a single construction phase. The new covered pavilion and tunnel closes a long-standing accessibility gap by giving residents east of the tracks direct access to the station from Randolph Avenue, rather than requiring a detour across the bridge.
On the rail side, the project added roughly 2.5 km of new track, bringing the Kitchener Line corridor to four tracks between Dupont Street and Lansdowne Avenue. The work also required realignment of the West Toronto Railpath, with a new community park built at Ernest Avenue as part of the mitigation package. Metrolinx is positioning the upgrade as one phase of a multi-project program intended to convert the Kitchener Line into two-way, all-day rapid transit service.
Key Project Data
| Parameter | Value |
|---|---|
| Project / Contract Name | Bloor GO/UP Station upgrades and Kitchener Line track expansion |
| Total Value | Not disclosed |
| Parties Involved | Metrolinx; construction contractor not identified in the announcement |
| Timeline / Completion | Completion announced July 31, 2026; construction start date not disclosed |
| Country / Corridor | Canada — Toronto, Ontario; GO Transit Kitchener Line between Lansdowne Avenue and Dupont Street |
How Does This Compare to Similar Projects?
North American commuter-rail capacity programs are typically measured in tens of corridor miles, making the Bloor project a targeted urban pinch-point fix rather than a full corridor expansion. Transit Systems Partners (TSP) managed the South Shore Line expansion in Indiana in 2025, which delivered 22 miles of new double track, 64 new signal and grade-crossing houses, and modifications to 24 existing locations (Source: Transit Systems Partners, 2025).
The Bloor works must therefore be judged as an enabling block within a larger network program, not a standalone capacity investment. The station-access tunnel also reflects a global pattern: urban rail transit infrastructure improved commuter mobility by 18% globally in 2025, with North America accounting for 11% of rail modernization demand (Source: Business Research Insights, 2025). No comparable per-kilometre cost figure for the Bloor track addition was publicly available at time of publication, nor was a completion date disclosed for the broader Kitchener Line transformation.
Editor’s Analysis
Metrolinx’s sequencing of station access and track delivery avoids the common failure mode of adding frequency to stations that cannot process passenger volumes efficiently. The provision of the Ernest Avenue park and Railpath realignment suggests the operator is treating local community buy-in as a precondition for urban corridor expansion, a cost that often exceeds track construction itself in dense Toronto neighbourhoods. With commuter mobility gains of 18% globally attributed to urban rail investment in 2025 (Source: Business Research Insights, 2025), the ridership payoff for Bloor will depend on how quickly Metrolinx translates the new four-track segment into published all-day frequencies on the Kitchener Line.
FAQ
Q: Does Bloor GO/UP Station now have entrances on both sides of the railway tracks?
A: Yes. The new covered pavilion and pedestrian tunnel provide direct station access from Randolph Avenue on the east side of the tracks. Previously, access was primarily from the west side via Bloor Street West.
Q: How many tracks now operate between Dupont Street and Lansdowne Avenue on the Kitchener Line?
A: The corridor now has four tracks on that segment following the installation of approximately 2.5 km of new rail. This configuration allows trains to pass one another at the station rather than queuing on single-track sections, a prerequisite for higher frequencies.
Q: What was the total cost of the Bloor GO/UP Station upgrades?
A: The total project value was not disclosed in Metrolinx’s announcement. The contractor responsible for construction was also not identified.