Introduction

The construction of Okehampton Interchange, a £15 million project, is progressing with the recent installation of key steel structures, including a footbridge, as part of the new station being built by Network Rail and its contractor Octavius. The station is slated to open in summer 2026 and will serve the Dartmoor Line, enhancing connectivity for West Devon, Torridge, and North Cornwall.

Key Infrastructure Installation

Over three nights, a 350-tonne crane was utilized to position steel structures from the station car park over the railway. These included a lift shaft, four columns for the staircase, and three staircase sections. Following this, the 25-meter-long footbridge was installed six meters above the railway in two sections. This bridge will connect the 200-space car park to the station’s single platform, which will be 100 meters long and supported by 107 coping stones.

Project Funding and Partnerships

The Okehampton Interchange project is funded through a successful bid by Devon County Council and West Devon Borough Council for Government funding, supplemented by contributions from both authorities. Rail Minister Lord Peter Hendy highlighted the £15 million in government support for the project, emphasizing its role in enhancing regional connectivity and modernizing services. The project involves partnerships between Network Rail, Great Western Railway, Devon County Council, and other stakeholders.

Anticipated Benefits

The new station aims to provide hourly train services, linking West Devon, Torridge, and North Cornwall with Exeter and beyond. West Devon Borough Council anticipates the station will boost local businesses by improving access for customers, staff, and suppliers, thereby attracting investment and supporting tourism. Devon County Council emphasizes the station’s role in expanding rail travel options, addressing congestion, and reducing carbon emissions. GWR anticipates that the station will bring train travel to the wider community of north Devon and benefit the local economy, residents, businesses, and leisure travelers.

Project Timeline and Future Steps

Work is currently ongoing, with completion expected in spring next year. Network Rail’s Programme Director, Bogdan Lupu, noted that the footbridge platform structure’s placement marks a significant project milestone. The station’s opening is scheduled for next year.

Last June 2025, we published an article about Renfe’s cutting-edge Aranjuez maintenance hub. Click here to read – Future of Rail: Renfe’s Railway Technology Hub, Aranjuez: Essential Guide

Conclusion

The Okehampton Interchange project continues to progress, with recent infrastructure installations bringing the station closer to its planned opening in summer 2026. The project, supported by Government funding and local council contributions, aims to improve regional connectivity and provide economic benefits to the local community.

Company Summary

Network Rail: A key player in the project, responsible for building the new station with its contractor Octavius.

Octavius: The contractor working with Network Rail on the construction of the new station.

Devon County Council: A key partner in the project, contributing funding and working alongside other stakeholders.

West Devon Borough Council: Another key partner, contributing funding and supporting the project.

Great Western Railway: A partner involved in the project’s development, contributing to the expansion of rail services.

“`