Suburban Rail Loop: Melbourne Rail Project Progress & Timeline
Suburban Rail Loop project in Melbourne is making substantial progress, debunking stagnation claims. Construction is underway at multiple sites, including stations and stabling yards.

Suburban Rail Loop Project Debunks Claims of Stagnation, Demonstrates Substantial Progress
Melbourne’s ambitious Suburban Rail Loop (SRL) project is actively progressing, with the Chief Executive Officer of the SRL Authority, Frankie Carroll, refuting criticisms of inactivity and emphasizing the significant on-the-ground developments. Speaking at the recent Urban Rail conference, Carroll directly addressed concerns surrounding the project’s momentum, presenting a detailed overview of ongoing construction efforts. The SRL East, encompassing six stations (Cheltenham, Clayton, Monash, Glen Waverley, Burwood, and Box Hill) and the Heatherton stabling yard, is the focus of this rapid development. This article delves into the specifics of the current works, the project’s timelines, and the substantial workforce dedicated to bringing this complex undertaking to fruition. The emphasis is on the progress made, the challenges being overcome, and the future implications for Melbourne’s public transport network.
Extensive Construction Activity Across Multiple Sites
The SRL project’s commitment to on-site development has resulted in a substantial workforce. “We’ve got 3000 people working on the project at the moment,” Carroll stated, highlighting the project’s scale. Work is underway at all six stations for the SRL East. This includes essential site preparations, such as utility relocations, site establishment, levelling, road modifications, and demolition. These ‘Initial and Early Works’ are being handled by Laing O’Rourke and are on schedule to be completed by January 2026, “on time and on budget,” according to Carroll. The projects also include the stabling yard being constructed at Heatherton, where significant progress has been reported.
Tunnel Boring Machine (TBM) Launch Site Preparations at Clarinda
A crucial element of the SRL involves tunneling operations, with the Clarinda site serving as the launch point for TBMs. Ground improvement works are underway in relation to the tunnel axis. Additionally, excavation for the D-walls, which stands for diaphragm walls, is taking place. D-walls are a technique for building concrete retaining walls within the ground, a critical aspect of tunneling construction. The first TBM is anticipated to commence work in approximately April 2025. This systematic preparation demonstrates the phased approach to launching the project’s underground infrastructure.
Heatherton Stabling Yard Nears Completion
The Heatherton stabling yard, intended to house, clean, and maintain 13 trains, is another area of focused development. Carroll reported the installation of steel struts and projected completion by the end of the year, with handover to the main contractor to follow shortly after. The power supply and the building itself are also in place. Energization is soon to begin to supply the TBMs with power. This signifies a significant milestone towards the operational readiness of the SRL East.
Burwood Station Construction: A Key Site for 2026 TBM Operations
At Burwood, excavation is anticipated to conclude by the end of July. All the necessary utility relocations have been finalized, and building demolition around the site has been accomplished. Preparations are proceeding for the arrival of TBMs at this site, also scheduled for 2026. This is a strong demonstration of the methodical and coordinated approach necessary for large-scale infrastructure construction.
Conclusion
The Suburban Rail Loop project is actively demonstrating that significant progress is being made, contrary to claims of inactivity. The recent statements by Frankie Carroll serve to inform stakeholders of the reality of the current progress. With work underway across multiple sites, from station construction to the crucial Heatherton stabling yard and tunnel preparations, the project is moving forward methodically. The ongoing efforts, including TBM launch site preparations and the planned rollout of major infrastructure components, highlight a commitment to the timely delivery of this essential public transport project. The project faces challenges and potential complexities, but the current progress points toward a positive outcome. The eventual opening of the SRL East in 2035 will have profound effects on Melbourne’s public transport infrastructure, increasing connectivity and alleviating congestion across the city. Further developments will be outlined in the August issue of Rail Express.



