HS2 Northolt Tunnel: High-Speed Rail Milestone in London, UK
HS2’s Northolt Tunnel excavation complete, a crucial step for UK high-speed rail.

Northolt Tunnel Excavation Complete: A Milestone for HS2’s London Route
HS2, the UK’s high-speed rail project, has reached a significant milestone with the completion of excavation for the 8.4-mile (13.5 km) Northolt Tunnel. This twin-bore tunnel, a vital link for HS2’s new high-speed trains, will connect West Ruislip to the future Old Oak Common super-hub station in west London. The project, undertaken by HS2’s London tunnels contractor Skanska Costain STRABAG JV (SCS JV), utilized four Tunnel Boring Machines (TBMs) to carve a path beneath the capital. The completion signifies a crucial step forward in delivering enhanced rail capacity and improved journey times for millions of rail users. This article explores the key aspects of the Northolt Tunnel project, from its complex engineering to its broader impact on the HS2 network and the industry.
Engineering Marvel: The TBMs at Work
The Northolt Tunnel, reaching depths of 35 meters below ground, was excavated using four TBMs. These colossal machines, manufactured by Herrenknecht AG, each weighing approximately 1,700 tonnes. Two TBMs, “Anne” and its twin, excavated the eastern section from Victoria Road in North Acton, with “Anne” completing its second bore in July 2024. The remaining two TBMs tackled the western section from West Ruislip. The TBMs’ journey involved a meticulous process. Each machine advanced at up to 38 meters per day, employing a 9.11-meter diameter cutterhead to bore through the London clay. Excavated material was removed via a conveyor system, with the extracted clay subsequently transported by rail to the London Logistics Hub for reuse across the UK. The tunnels themselves vary in width: 8.10m in the east and 8.80m in the west to account for aerodynamic demands on high-speed trains.
Challenges and Innovations in Construction
The construction of the Northolt Tunnel presented unique challenges, including the high water pressure in the ground at Green Park Way, where all four TBMs concluded their drives. To overcome this, the TBMs finished their work in steel reception cans installed in underground shafts. This innovative “reception can” method allowed engineers to maintain pressure while applying sealant from the tunnel lining, preventing water ingress before depressurizing the can and removing the TBM. This process showcases the expertise in the industry, utilizing cutting-edge technology to ensure the project’s safe and efficient completion. The utilization of pre-fabricated concrete segments, each weighing up to 7 tonnes and transported by rail from Hartlepool, further highlights the project’s efficiency and commitment to minimizing environmental impact.
The Scale of the Project
The Northolt Tunnel is a key component of the larger HS2 project, and the excavation required a massive effort. The four TBMs excavated a total of 4,160,000 tonnes of London clay and lined the tunnel with 14,300 concrete tunnel rings, comprised of 94,233 individual concrete segments. The tunnel’s design includes 34 cross passages between the twin bores, and five headhouses, which house the ventilation shafts to regulate air quality, temperature, and smoke extraction in the event of a fire. This scale highlights the complexity and ambition of HS2, reflecting a long-term investment in the UK’s rail infrastructure. The construction project is estimated to have generated £20bn in economic benefit.
Impact on the HS2 Network and the Future of Rail
The completion of the Northolt Tunnel excavation marks a significant step toward the realization of HS2, a project that aims to increase rail capacity and improve connectivity across the UK. The project’s success is a result of the industry’s commitment to overcoming complex challenges, innovating, and adhering to construction timelines. Now that the excavation is complete, the focus shifts to constructing the flat tunnel invert on the base where the high-speed tracks will be laid. The HS2 Ltd Chief Executive, Mark Wild, is overseeing a “major reset” to ensure the railway is delivered at the lowest reasonable cost. HS2 is expected to bring about positive changes to the industry.
Conclusion
The completion of excavation for the Northolt Tunnel represents a major milestone for HS2, showcasing the engineering expertise and collaborative efforts involved in delivering this ambitious infrastructure project. This project reinforces the importance of innovation, such as the reception can technique and efficient segment transport, which supports minimizing environmental impacts and construction risks. The project’s completion brings the promise of increased rail capacity and improved journey times for millions of rail users closer to reality. The completion of the Northolt Tunnel adds to a growing portfolio of infrastructure projects in the UK, demonstrating the industry’s commitment to strengthening the rail network and enhancing rail travel. The success of this project can pave the way for continued advancements in the rail sector, helping the HS2 plan for future development.


