Balfour Beatty VINCI Completes 37-Metre HS2 Overbridge
Balfour Beatty VINCI confirmed completion of the 37-metre A45 road bridge near Bickenhill, placing 13 precast beams over four future HS2 tracks in late 2026.

BICKENHILL, UNITED KINGDOM – High Speed 2 joint venture Balfour Beatty VINCI completed the eastbound deck of the Coventry Road overbridge along the A45 corridor in late 2026. The 2,000-tonne structure required the installation of 46 foundation piles reaching depths of 23 metres to support traffic during line excavation. Structural completion of the entire two-phase crossing is scheduled for late 2027, ahead of final highway integration in summer 2028.
What Is the Full Scope of This Project?
The Coventry Road overbridge contract delivers a two-stage grade separation carrying the dual-carriageway A45 over four high-speed tracks heading toward the future HS2 Interchange Station. Engineers utilised top-down construction techniques to remove 75,000 tonnes of earth beneath the operating highway, preventing long-term carriageway shutdowns. Phase one placed 13 pre-stressed, pre-cast concrete beams across a 37-metre span alongside 13 parapet units to establish a temporary alignment for eastbound traffic. Phase two mirrors this engineering sequence on the westbound side beginning in early 2027, clearing the rail trace for four tracks feeding two 425-metre island platforms one mile north at Interchange Station. Specific civil engineering costs for this individual bridge package were not disclosed by HS2 Ltd.
Key Project Data
| Parameter | Value |
|---|---|
| Project / Contract Name | Coventry Road (A45) Overbridge / HS2 Phase One Civil Works |
| Total Value | Not disclosed |
| Parties Involved | HS2 Ltd, Balfour Beatty VINCI (BBV), National Highways |
| Timeline / Completion | Structural completion late 2027; highway opening summer 2028 |
| Country / Corridor | United Kingdom / West Midlands (London–Birmingham Phase One) |
How Does This Compare to Similar Projects?
Constructing complex four-track grade separations under live trunk corridors presents higher unit costs and longer delivery schedules than standard greenfield high-speed alignments. By comparison, Austin’s CapMetro allocated $32,184,000 in 2024 to double-track sections of its Red Line commuter corridor across less congested rights-of-way (Source: CapMetro, 2024). On an international scale, national network spend figures show sharp contrasts in output: China State Railway Group invested 901.5 billion yuan ($128.9 billion) in 2025 to construct 2,862 kilometres of high-speed track within a single year (Source: China State Railway Group, 2026). In Europe, Germany channeled €19 billion to €22 billion into DB InfraGO network upgrades during 2025, prioritizing asset renewal across dense multi-modal hubs (Source: Reuters, 2025). Independent verification of the standalone construction budget for the Coventry Road overbridge structure was not available at time of publication.
Editor’s Analysis
Top-down structural execution on the A45 reflects the severe technical trade-offs HS2 faces when navigating critical arterial roads in the West Midlands urban fringe. Delivering civil assets in halves protects regional freight corridors but extends structural schedules, pushing final surface completion out to mid-2028. European infrastructure managers face similar capital constraints; France’s multi-year SNCF Réseau contract committed an extra €1.5 billion annually only from 2028 onward, showing how major rail programs increasingly stage works to absorb high baseline civil engineering costs (Source: French Ministry of Transport, 2026).
FAQ
Q: Why is the Coventry Road overbridge being constructed in two separate halves?
A: Balfour Beatty VINCI adopted a two-phase sequence to keep the active A45 highway open to traffic while excavating 75,000 tonnes of subsoil beneath. This staging allows traffic to divert onto the newly completed eastbound deck before westbound demolition begins.
Q: What railway infrastructure will pass underneath the completed bridge?
A: The excavated corridor will host four high-speed tracks heading to HS2’s Interchange Station located one mile to the north. These tracks will directly connect to two 425-metre passenger platform islands serving the West Midlands hub.
Q: When will motorists drive on the final road layout?
A: Structural work on the second half of the overbridge will finish in late 2027, followed by permanent surfacing, drainage, and lighting installation. National Highways and HS2 expect the permanent dual-carriageway alignment to open by summer 2028.