Alstom Hits 100th ERTMS Train Milestone in Norway
Alstom delivers the 100th ERTMS-retrofitted train in Norway, modernizing its rail network with satellite-based tech, boosting capacity and cutting costs.

- Alstom has delivered the 100th ERTMS-retrofitted train for Norway’s national signaling program, which targets a total of over 350 vehicles.
- The project is progressing at a rate of 3-4 trains per month, using Alstom’s Onvia Cab platform with a unique satellite-based positioning system.
- This milestone advances Norway’s strategy to increase network capacity and interoperability while lowering long-term maintenance costs by reducing trackside equipment.
OSLO, NORWAY – Alstom has reached a key production milestone in Norway’s national digital railway program with the delivery of its 100th train equipped with the European Rail Traffic Management System (ERTMS). The project, one of Europe’s most extensive signaling upgrades, aims to retrofit Alstom’s on-board system across a fleet of more than 350 passenger, freight, and maintenance vehicles.
| Category | Specification / Detail |
|---|---|
| Project | Norway ERTMS National Implementation |
| Total Scope | Over 350 rail vehicles |
| Current Status | 100 vehicles delivered; 2 fleets fully upgraded (Bane NOR) |
| On-board System | Alstom Onvia Cab ERTMS Platform |
| Production Rate | 3-4 modernized trains per month |
| Key Stakeholders | Alstom, Bane NOR, Norske Tog, Vy, SJ Norge, freight operators |
Operational & Technical Details
The retrofitting work is performed entirely within Norway. Alstom’s facilities in Grorud (Oslo) and Marienborg (Trondheim) handle the installation and testing. The core technology is Alstom’s Onvia Cab on-board signaling solution. It is compatible with both new and existing rolling stock.
A key technical adaptation for this project is a new-generation position measurement system. It relies on satellite positioning to ensure reliable operation in Norway’s harsh climatic conditions. This system is critical for reducing dependency on physical, ground-based signaling equipment, a central goal of the ERTMS strategy.
Market Impact Analysis
This milestone solidifies Alstom’s role as the primary technology partner for Norway’s ambitious signaling modernization. Successfully deploying a satellite-based positioning system in challenging Nordic weather serves as a powerful case study for Alstom, potentially influencing procurement decisions in other regions with similar climates. For Norway, the program’s progress is a critical step toward a fully interoperable, higher-capacity rail network with significantly lower long-term maintenance expenditures for infrastructure manager Bane NOR.
FAQ: Quick Facts
What is the main value of this contract?
The project’s value is strategic, focused on modernizing Norway’s national rail network to the ERTMS standard. This will increase network capacity, improve punctuality, enable cross-border interoperability, and reduce long-term infrastructure maintenance costs. No specific monetary value has been disclosed.
When is the expected completion date?
The source material does not specify a final completion date. With over 250 vehicles remaining to be equipped at a rate of 3-4 per month, the program is scheduled to continue for several more years.