Network Rail Opens Thorpe Park Rail Station Consultation
Network Rail opened public consultation on Thorpe Park Rail Station, a 300-space park-and-ride with two platforms in Leeds, and it now runs to 15 September.

LEEDS, United Kingdom – Public consultation on Thorpe Park Rail Station opened and runs until the end of Tuesday 15 September, covering a two-platform station on the TransPennine Leeds–York line between Cross Gates and Garforth. Network Rail is delivering the scheme with the West Yorkshire Combined Authority (WYCA), in consultation with Leeds City Council, targeting a minimum of two trains per hour in each direction toward Leeds–York and Leeds–Hull. Journey times from the new station to Leeds Station are stated at 10–12 minutes.
What Is the Full Scope of This Project?
Thorpe Park Rail Station comprises two train platforms, a lift and footbridge for step-free access, ticket machines, cycle parking and a 300-space car park with Electric Vehicle charging points, disabled bays and a drop-off/pick-up point. The station is positioned next to Thorpe Park Business Park, whose existing tenant base the developer Scarborough Group International puts at 7,500 employees, and adjacent to The Springs retail and leisure destination. A full business case will be submitted later this year for discussion at a future WYCA meeting, with construction set to start in 2027. The 300 spaces are intended to absorb park-and-ride demand that currently pressures Garforth Station’s car park, which the source describes as being at capacity.
Key Project Data
| Parameter | Value |
|---|---|
| Project / Contract Name | Thorpe Park Rail Station |
| Total Value | Not disclosed |
| Parties Involved | Network Rail; West Yorkshire Combined Authority; Leeds City Council (consultation); Scarborough Group International and Redrow Yorkshire (supporting developers) |
| Timeline / Completion | Consultation closes 15 September; full business case later in 2025; construction start 2027 |
| Country / Corridor | United Kingdom – TransPennine route, Leeds to York section, between Cross Gates and Garforth |
How Does This Compare to Similar Projects?
Thorpe Park’s capital cost has not been published, which prevents a direct cost-per-platform benchmark against WYCA’s existing station portfolio. The authority has delivered new stations at Low Moor, Kirkstall Forge and Apperley Bridge and states it has built or upgraded ten bus and rail stations for a combined £111 million, an average of roughly £11.1 million per station across a portfolio that includes bus infrastructure as well as rail. (Source: West Yorkshire Combined Authority, 2025)
Activity elsewhere on the same Leeds corridor shows mixed delivery risk. Leeds Station is undergoing infrastructure enhancements under the Department for Transport’s north-east programme, with £55 million secured in October 2024 for new operational accommodation and strengthening works, while Transforming Cities Fund projects in Harrogate, Selby and Skipton include pedestrian and cycle improvements around Leeds Station with contracts expected to be signed in November 2025. (Source: Department for Transport, 2024; North Yorkshire Council, 2025) By contrast, work on White Rose Station has been paused over a “difference of opinion” between the funding body and a landowner, with the project’s cost exceeding its original budget — a precedent directly relevant to Thorpe Park’s land assembly and cost profile. (Source: BBC News, 2025)
Wider market conditions are supportive: the UK rail market is projected to reach USD 185.31 billion by 2034 at a CAGR of 6.65% from 2026 to 2034, and global high-speed rail investment rose 24% in 2025. (Source: Market Data Forecast, 2025; Business Research Insights, 2025) On the supply side, FS Group and Certares have partnered on high-speed rail growth in the UK and France with an investment programme of around €1 billion, indicating capital availability at the upper end of the market rather than at the suburban station tier Thorpe Park occupies. (Source: Railway News, 2025)
Editor’s Analysis
Thorpe Park is a demand-capture station rather than a capacity project: 300 park-and-ride spaces on a corridor where Garforth is already full is a direct substitution play, and the 7,500-employee business park gives it a captive weekday base that most new stations lack. The unresolved variable is cost disclosure — WYCA’s £111 million across ten stations implies a modest per-asset envelope, and the White Rose pause shows how quickly a landowner disagreement can freeze a station on this same Leeds network. Watch whether the business case due later this year publishes a capital figure and a land acquisition status, since those two data points will determine whether the 2027 construction start holds.
FAQ
Q: Where exactly will Thorpe Park Rail Station be built?
A: It will sit next to Thorpe Park Business Park on the Leeds to York section of the TransPennine railway line, between Cross Gates and Garforth in east Leeds. The station serves The Springs retail and leisure destination and the surrounding residential developments.
Q: How much will Thorpe Park Rail Station cost and when will it open?
A: No capital cost has been disclosed by Network Rail or the West Yorkshire Combined Authority. The full business case is due later this year, construction is scheduled to start in 2027, and no opening date has been confirmed.
Q: How will Thorpe Park Rail Station affect existing services and stations?
A: The design supports a minimum of two services per hour in each direction on the Leeds–York and Leeds–Hull routes, with journey times to Leeds Station of 10–12 minutes. The 300-space car park is intended to relieve pressure on Garforth Station’s car park, which is at capacity.
Q: How can the public respond to the consultation?
A: The consultation is open now and closes at the end of Tuesday 15 September, with plans available through the WYCA and Network Rail consultation channels. Leeds City Council Executive Member for Transport and Planning Peter Carlill has encouraged residents, workers and visitors to submit views.
Note: Independent verification of the Thorpe Park Rail Station capital cost, land acquisition status and platform construction methodology was not available at time of publication; neither WYCA nor Network Rail has published these figures in the consultation materials reviewed.